Pillar 4: Infrastructure Development

Goal 3

Activity 1: Completion of ongoing bitumen roads.

Work Breakdown Structure

44%

Activity Progress

Complete upgrading of the Windhoek - Okahandja road to the dual carriageway

Sub Activity Description:

The 27 km Section 4 from Dobra River to Omakunde Interchange, with four major bridges and four interchanges, has been completed. Phase 4A extension is 21 km, beginning from Omakunde River to Otjiwarongo interchange. This road will be completed in 2022.
Start Date: 2019-07-27
End Date: 2022-07-26
Duration: 50
Months
Status: Ongoing
Resource: Roads Authority of Namibia
Responsible Entity: Roads Authority of Namibia
Quality: COLTO
Cost: N$ 997,082,367.00
Risk: Covid-19 Associated Risk, Financial Risk, Resource Risk, Schedule Risk, Quality Risk

Activity Progress

Upgrade Swakopmund - Henties Bay - Kamanjab road

Sub Activity Description:

Upgrade of the Swakopmund to Kamanjab to bitumen standard. The Works are divided into two (2) Phases and four (4) sections. Phase 1 Section A, Swakopmund to 20 km beyond Henties Bay, works are complete with section in the Defects Notification Period. Phase 1 Section B, 20 km beyond Henties Bay to Uis, is currently under construction.
Start Date: 2021-7-9
End Date: 2024-1-8
Duration: 913
Days
Status: Ongoing
Resource: Roads Authority of Namibia
Responsible Entity: Roads Authority of Namibia
Quality: COLTO
Risk: Covid-19 Associated Risk, Financial Risk, Schedule Risk, Quality Risk

Activity Progress

Upgrade Swakopmund-Walvis Bay road to dual carriageway

Sub Activity Description:

End Date: 2020-10-19
Days
Status: Complete
Resource: Roads Authority of Namibia
Responsible Entity: Roads Authority of Namibia
Quality: COLTO
Risk: Covid-19 Associated Risk, Financial Risk, Resource Risk, Schedule Risk, Quality Risk

Activity Progress

Upgrade Windhoek - Hosea Kutako International Airport Road to dual carriageway

Sub Activity Description:

The Widhoek - Hosea Kutato International Airport Road project is divided into three (3) phases with Phase 1 complete. Construction is underway for Phase 2A and Contractor is mobilising for Phase 2B.
Start Date: 2016-01-18
End Date: 2024-07-05
Duration: 4550
Days
Status: Ongoing
Resource: Roads Authority of Namibia
Responsible Entity: Roads Authority of Namibia
Quality: COLTO
Risk: Covid-19 Associated Risk, Financial Risk, Resource Risk, Schedule Risk, Quality Risk

Activity Progress

Complete Gobabis - Aranos Road

Sub Activity Description:

Construction of this road is being done in two phases, Phase 1 Gobabis to Onderombapa, and Phase 2 Onderombapa to Aranos. Phase 1 is complete with Phase 2 currently under construction.
Start Date: 2019-10-01
End Date: 2023-12-31
Duration: 1552
Days
Status: Ongoing
Resource: Roads Authority of Namibia
Responsible Entity: Roads Authority of Namibia
Quality: COLTO
Risk: Covid-19 Associated Risk, Financial Risk, Resource Risk, Schedule Risk, Quality Risk

Related Projects

WO Roads3
Region: Khomas
Sector: Roads
Project Progress
0%