Pillar 4: Infrastructure Development

Goal 2

Activity 1: Ensure Access to Water for Human Consumption and Industrial Activities

 

 

Work Breakdown Structure

5%

Activity Progress

A. Expand rural water supply infrastructure to increase

Sub Activity Description:

1.Drilling of 57 boreholes Kunene, Omusati, Erongo, Zambezi, Omaheke, Hardap, Kavango East, Kavango West, Ohangwena and !Kharas Regions. 2.Installation of 37 boreholes 3.Rehabilitation of 23 water point infrastructure in Omusati, Otjozondjupa and Oshikoto Regions. 4.Cleaning of 12 boreholes 5.Construction of 15km pipeline from Ohamaremba to Okangwati 6.Construction of Ozondati-Omatjete Pipeline 7.Construction and Rehabilitation of 5 Earthdams in Omusati Region 8.Procurement of in house material Countrywide 9.Purchasing of 3 10 000L water tankers 10.Upgrade and expansion of Ruacana South Water Supply Scheme phase 1. 11.Upgrade and expansion of Otjombinde Water Supply Scheme. 12.Upgrade and expansion of Katima/Kongola Water Supply Scheme. Phase 3. 13.Upgrade and expansion of King Kauluma- Omutsegonime pipeline 14.Upgrade and expansion of Katima Ngoma Water Supply Scheme Phase 3. 15.Upgrade and expansion of Katima Ngoma Water Supply Scheme Phase 4. 16.Upgrade and expansion of Katima Ngoma Water Supply Scheme Reservoir. 17.Upgrade and expansion of Iitapa – Okeeholongo Water Supply Scheme Phase 2.
Start Date: 2021-07-01
End Date: 2025-04-30
Duration: 4
Years
Status: Ongoing
Resource: OPM/Ministry of Agriculture, Water and land reform
Responsible Entity: OPM (Disaster Risk Management Unit and MAWLR (Directorate Water Supply and Sanitation Coordination)
Quality: SANS
Cost: N$ 632,330,228.50
Risk: Covid-19 Associated Risk, Financial Risk, Resource Risk, Schedule Risk, Quality Risk

Activity Progress

B. Commence Phase 1 development of the Ohangwena aquifer.

Sub Activity Description:

1. Procure Consultant including an Independent Environmental Assessment Practitioner 2. Consolidate previous studies with specific reference to Omafo-Eenhana scheme and Omakango-Onambutu-Eenhana scheme, which will result in the final concept document proposal. Identify Sites, drill two (2) boreholes at Eenhana, one duty and one stand-by, and do pump testing of boreholes. 3. Undertake preliminary design and cost estimates on the Omafo-Eenhana and Omakango-Onambutu-Eenhana Schemes, focusing on the development of Ohangwena II aquifer at Oshandi and Eenhana, the Omakango-Onambutu pipeline replacement and related pipelines to Eenhana and Oshandi 4.Compile the Environmental and Social Impact Assessment (ESIA) study and obtain Environmental Clearance Certificate (ECC) 5. Undertake detailed designs based on the concept document proposal and finalisation of detail design drawings; prepare tender documents and procure a contactor. 6. Construct the infrastructure system to improve sufficiency of the bulk water supply capacity for the Omafo-Eenhana and Omakango-Onambutu-Eenhana Schemes to meet the 2037 water demand.
Start Date: 2021-09-21
End Date: 2024-09-12
Duration: 29
Months
Status: Ongoing
Resource: NAMWATER
Quality: SANS
Cost: N$ 17 000 000.00
Risk: Covid-19 Associated Risk, Financial Risk, Resource Risk, Schedule Risk, Quality Risk
95%

Activity Progress

C. Complete the permanent pumping installation at Calueque dam to secure water supply to this region for the long term.

Sub Activity Description:

1. Mobilization and Demobilization of contractor’s technical staff. 2. Pre-Assessment of the hydraulic Network; Pump installations; Electrical installations & Maintenance, Tests and Parametrization of the protection relays. 3. Actual Commissioning.
Start Date: 2021-01-21
End Date: 2021-04-07
Duration: 11
Weeks
Status: Complete
Resource: NAMWATER
Quality: SANS
Cost: N$5 500 000.00
25%

Activity Progress

D. Refurbish and upgrade the Calueque to Oshakati canal system

Sub Activity Description:

1. Omahene-Olushandja canal refurbishment 2. Ogongo canal end section 3. Ogongo-Oshakati canal rehabilitation: Oshikuku bypass 4. Ogongo-Oshakati canal refurbishment 5.Olushandja-Ogongo canal refurbishment
Start Date: 2021-05-04
End Date: 2025-03-31
Duration: 5
Years
Status: Ongoing
Resource: NAMWATER
Responsible Entity: NAMWATER
Quality: SANS
Cost: N$374,600,000
Risk: Covid-19 Associated Risk, Financial Risk, Resource Risk, Schedule Risk, Quality Risk

Activity Progress

E. Develop Abenab aquifer and link it to the ENWC

Sub Activity Description:

1. Expression of Interest (EoI) for Consultancy Services 2. Evaluation of Consultancy Services and Contract awards. 3. Undertake detailed design, research and documentation 4. Bid preparation and evaluation for construction 5. Construction/Project execution 6. Closeout and Commissioning
Start Date: 2022-10-04
End Date: 2028-04-04
Duration: 6
Years
Status: On Hold
Resource: NAMWATER
Quality: SANS
Risk: Covid-19 Associated Risk, Financial Risk, Resource Risk, Schedule Risk, Quality Risk

Activity Progress

F. Double up existing direct potable water reclamation works in Windhoek.

Sub Activity Description:

1. Prepare terms of reference, procure Consultant for, and undertake Technical Feasibility study 2. Prepare bidding documents & procure Consultants responsible for the reference design and compilation of bidding documentation to appoint DBO(T) Contractor 3. Undertake reference design, preparation of Scope of Services & prepare bidding documentation to procure the DBO(T) Contractor, provide Contract Management & supervision services during design and Construction phase 4.KFW Concessional Finance Agreements: Inter-governmental negotiations and commitment with AG, MoF and KFW’s final approval (Deadline for securing finance and achieving financial close Dec 2022) 5. Procurement of Contractor (DBO(T)) for the Design, Construction (and operation) of the Reclamation Plant 7. Testing, commissioning, and achieving Commercial Operate starting
Start Date: 2021-03-01
End Date: 2026-04-10
Duration: 64
Months
Status: On Hold
Resource: City of Windhoek
Quality: SANS
Cost: N$ 723 000 000 .00
Risk: Covid-19 Associated Risk, Financial Risk, Resource Risk, Schedule Risk, Quality Risk

Activity Progress

G. Replace existing Reservoirs and establish a Purification Plant at Rundu.

Sub Activity Description:

1.Procure Consultant including an Independent Environmental Assessment Practitioner 2.Investigate suitable sites for the expansion of the storage reservoirs for the Rundu and N’karapamwe schemes. Investigate and recommend the most suitable points of connection for the Masivi and Kayengona water supply schemes from Rundu Town; Do preliminary design, and cost estimates; 3. Compile the Environmental and Social Impact Assessment (ESIA) study and obtain Environmental Clearance Certificate (ECC) 4.Undertake detailed design for the new raw water abstraction and conveyance system; a 40MLD Water Treatment Plant (WTP); a Potable water conveyance system to Rundu and N’karapamwe existing storage reservoirs. 5. Compile tender documents and procure a contractor 6. Upgrade parts of the existing water supply scheme; Construct a raw water abstraction and conveyance system; a WTP; a Potable water conveyance system to Rundu and N’karapamwe existing storage reservoirs and decommission the old (redundant) infrastructure at Rundu.
Start Date: 2021-09-21
End Date: 2025-04-28
Duration: 36
Months
Status: Ongoing
Resource: NAMWATER
Quality: SANS
Cost: N$ 28 000 000.00
Risk: Covid-19 Associated Risk, Financial Risk, Resource Risk, Schedule Risk, Quality Risk

Activity Progress

H. Commence Phase 1 of National seawater desalination plant by either purchasing and upgrading the Orano Plant or building a new plant.

Sub Activity Description:

1. Appoint Consultants, undertake EIA, obtain Environmental Clearance Certificates 2. Appoint Tender Agent, prepare bidding documents for EPC/DBOT 3. Obtain funding. 4.Appoint developer(s) of new desalination plant & associated water conveyance & storage infrastructure 5.Design & construct new 20 Mm3/a desalination plant & associated water conveyance & storage infrastructure 6.Operate & maintain plant and handover to NamWater (This duration is based on the PPP agreement)
Start Date: 2021-09-21
End Date: 2025-07-21
Duration: 6
Years
Status: On Hold
Resource: NAMWATER
Quality: SANS
Cost: N$ 3,165,100,000
Risk: Covid-19 Associated Risk, Financial Risk, Resource Risk, Schedule Risk, Quality Risk

Activity Progress

I. Extend and upgrade Oshakati Purification Plant by 2025.

Sub Activity Description:

1.Procure Consultant including an Independent Environmental Assessment Practitioner 2.Investigate options for extending the treatment capacity, preliminary design, and cost estimates; 3.Compile the Environmental and Social Impact Assessment (ESIA) study and obtain Environmental Clearance Certificate (ECC) 4.Undertake detailed design for the new water supply infrastructure (50MLD Water Treatment Plant (WTP) & a 2 weeks capacity Raw water storage dam) 5.Compile tender documents for the procurement of a contractor 6.Construct WTP & Raw Water storage dam24 months
Start Date: 2021-09-21
End Date: 2025-01-06
Duration: 37
Months
Status: Ongoing
Resource: NAMWATER
Quality: SANS
Cost: N$12 000 000.00
Risk: Covid-19 Associated Risk, Financial Risk, Resource Risk, Schedule Risk, Quality Risk

Activity Progress

J. Omdel-Wlotzkasbaken pipeline replacement

Sub Activity Description:

1 Prepare bidding documents & procure Environmental Consultants 2 Undertake environmental work (Scoping, EIA & EMP) and obtain ECC 3 Undertake prelim design & cost estimate for 10.3 km, 700 mm dia. DCI above ground pipeline section, pump station 4 Undertake final design & prepare bidding documents 10.3 km, 700 mm dia. DCI above ground pipeline section, pump station 5 Procure contractor to lay 10.3 km, 700 mm dia. DCI above ground pipeline section 6 Construct 10.3 km, 700 mm dia. DCI above ground pipeline section
Start Date: 2021-09-21
End Date: 2025-05-25
Duration: 36
Months
Status: Ongoing
Resource: NAMWATER
Quality: SANS
Cost: N$183,840,000
Risk: Covid-19 Associated Risk, Financial Risk, Resource Risk, Schedule Risk, Quality Risk, Other
25%

Activity Progress

K. Kuiseb Collector 2-Schwarzekuppe-Swakopmund Pipeline Replacement Phases 2b and 3.

Sub Activity Description:

1Phase 2b: Construct 23.3 km, 600 mm dia, DCI above ground pipeline 1.1Procurement and Delivery of Pipe fittings 100% 1.2Manufacturing the metal shuttering 100% 1.3Set out the pipeline route 100% 1.4Site Clearance100% 1.5Construction of new pipeline (April 2022)73% 1.6Connection to existing pipeline (April 2022)0% 1.7Final Inspection (May 2022)0% 1.8Commissioning and takeover (June 2022) 0% 2Phase 3: Construct 8km, GRP and 3.0 km, 710 mm dia. HDPE below ground pipeline sections 2.1Undertake final design and prepare bidding documents 2.2Procure contractor 2.3Construct 5.0 km, 600 mm dia. GRP and 3.0 km, 710 mm dia. HDPE below ground pipeline sections
Start Date: 2021-09-21
End Date: 2024-05-27
Duration: 28
Months
Status: Ongoing
Resource: NAMWATER
Quality: SANS
Cost: N$354,510,000
Risk: Covid-19 Associated Risk, Financial Risk, Resource Risk, Schedule Risk, Quality Risk, Other

Related Projects

placeholder-image
Region: Kavango East
Sector: Water Infrastructure
Project Progress
0%

Pillar 4: Infrastructure Development

placeholder-image
Region: Khomas
Sector: Water Infrastructure
Project Progress
0%

Pillar 4: Infrastructure Development

placeholder-image
Region: Otjozondjupa, Omaheke, Khomas
Sector: Water Infrastructure
Project Progress
0%

Pillar 4: Infrastructure Development

CANAL 1
Region: Oshana
Sector: Water Infrastructure
Project Progress
0%

Pillar 4: Infrastructure Development

placeholder-image
Region: Kunene, Omusati, Oshana, Ohangwena, Oshikoto
Sector: Water Infrastructure
Project Progress
0%

Pillar 4: Infrastructure Development

placeholder-image
Region: Ohangwena
Sector: Water Infrastructure
Project Progress
0%

Pillar 4: Infrastructure Development