Work Breakdown Structure

13%

Activity Progress

Train 400 police officers, social workers, health care workers, youth officers in providing services for GBV survivors by the end of the HPP period.

Sub Activity Description:

Conduct training for Social workers, Police Officers, Health Care workers, Youth Officers on Standard Operating Procedures for Shelters for GBV/VAC.
Start Date: 2021-04-01
End Date: 2025-03-31
Duration: 48
Months
Status: Ongoing
Responsible Entity: Ministry of Health and Social Services, Ministry of Gender Equality, Poverty Eradication and Social Welfare, NAMPOL
Risk: Covid-19 Associated Risk, Financial Risk, Resource Risk, Schedule Risk, Quality Risk
12%

Activity Progress

Train 390 clinical and administrative personnel in all health facilities by the end of the HPP period.

Sub Activity Description:

Y1- 2021-2022 - 90 Clinical and Administrative Personnel. Y2- 2022-2023 - 100 Clinical and Administrative Personnel. Y3- 2023-2024 - 100 Clinical and Administrative Personnel. Y4- 2024-2025 - 100 Clinical and Administrative Personnel.
Start Date: 2021-04-01
End Date: 2025-03-31
Duration: 48
Months
Status: Ongoing
Resource: MOHSS
Responsible Entity: Ministry of Health and Social Services
Quality: ISO 9001
Risk: Covid-19 Associated Risk, Financial Risk, Resource Risk, Schedule Risk, Quality Risk
75%

Activity Progress

Finalise and implement the National Plan of Action on Violence Against Children.

Sub Activity Description:

Finalize and implement plan
Start Date: 2022-04-01
End Date: 2025-03-31
Duration: 36
Months
Status: Ongoing
Resource: MGEPESW
Responsible Entity: Ministry of Gender Equality, Poverty Eradication and Social Welfare
Quality: IS0 9001
Cost: N$152 000
Risk: Covid-19 Associated Risk, Financial Risk, Resource Risk, Schedule Risk, Quality Risk
75%

Activity Progress

Finalise and implement national strategy for Children Living and Working on the Streets.

Sub Activity Description:

Finalize and implement programs - 30 November 2021
Start Date: 2021-04-01
End Date: 2021-11-30
Duration: 8
Months
Status: Ongoing
Resource: MGEPESW
Responsible Entity: Ministry of Gender Equality, Poverty Eradication and Social Welfare
Quality: ISO 9001
Cost: N$590 000
Risk: Covid-19 Associated Risk, Financial Risk, Resource Risk, Schedule Risk, Quality Risk

Activity Progress

Establish infrastructure and rehabilitative programmes for Children Living and Working on the Streets, and children in conflict with the law.

Sub Activity Description:

Hold consultative meetings with key stakeholders on the development of programs Renovate Farm Kaukurus - Phase 1 Procure materials, equipment, seeds, fertilizers for the implementation of rehabilitative programs Implement programs at Farm Kaukurus
Start Date: 2021-04-01
End Date: 2025-03-31
Duration: 48
Months
Status: Ongoing
Resource: MGEPESW
Responsible Entity: Ministry of Gender Equality, Poverty Eradication and Social Welfare
Quality: SANS
Cost: N$7 100 00
Risk: Covid-19 Associated Risk, Financial Risk, Resource Risk, Schedule Risk, Quality Risk
25%

Activity Progress

Promulgate the Child Justice Bill by 2022.

Sub Activity Description:

CCL, Legal Drafters, AG - 01 Oct 21 - 31 Dec 21. National Assembly/National Council -03 Jan 22 - 04 Aug 22. Promulgate Bill 05 Aug 22 - 05 Sep 22 .
Start Date: 2021-10-01
End Date: 2022-09-22
Duration: 11
Months
Status: Ongoing
Resource: MOJ
Responsible Entity: Ministry of Justice
Cost: N$83 000
Risk: Covid-19 Associated Risk, Financial Risk, Resource Risk, Schedule Risk

Related Projects

Train 400 police officers, social workers, health care workers, youth officers in providing services for GBV survivors
Region: Countrywide
Sector: Gender-Based Violence
Project Progress
0%

Pillar 3: Social Progression

Promulgate the Child Justice Bill
Region: Countrywide
Sector: Social Welfare
Project Progress
0%

Pillar 3: Social Progression