Activity 4: Avail sufficient quantities of water for mining industry.

The Erongo Region holds great potential for the expansion of productive economic activity as it pertains to waterintensive industries and remains a critical engine of growth. A binding constraint is the lack of a viable solution to increase the quantity of affordable water to the industrial and mining sector based in the outskirts of Swakopmund and Walvis Bay. The Government will complete an initial feasibility study on a greenfield desalination plant in the fourth quarter of the 2021/22 financial year. Commensurately, Government will also explore the potential of meeting part of the water needs through a possible public private partnership (PPP) with the operators of the existing desalination plant in the Erongo region. Feedback on this approach is expected in the first quarter of the 2021/22 financial year.

Work Breakdown Structure

Activity Progress

Desalination Plant

Sub Activity Description:

The Government will complete an initial feasibility study on a greenfield desalination plant in the fourth quarter of the 2021/22 financial year. Commensurately, Government will also explore the potential of meeting part of the water needs through a possible public-private partnership (PPP) with the operators of the existing desalination plant in the Erongo region. Feedback on this approach is expected in the first quarter of the 2021/22 financial year.
Start Date: 2021-09-22
End Date: 2024-12-04
Duration: 25
Months
Status: Ongoing
Resource: Ministry of Agriculture, Water and Land Reserve, Namwater
Responsible Entity: Ministry of Agriculture, Water and Land Reserve
Risk: Covid-19 Associated Risk, Financial Risk, Resource Risk

Related Projects

DESAL
Region: Erongo
Sector: Water
Project Progress
0%